West Terre Haute Water Treatment Plant

MSI Construction served as the General Contractor for the Town of West Terre Haute New Water Treatment Plant, and it was completed in the spring of 2020. The $2.455 million dollar project addresses longstanding problems with brown water while installing new, larger water lines will improve the towns water pressure.



This project includes the construction of a new water treatment plant building, one packaged pre-engineered treatment unit, two high service pumps, chemical feed equipment, mechanical and HVAC systems, SCADA system medication, new access drive and parking areas, and associated water mains, valves, plumbing, sanitary sewers, earthwork, and electrical work. The con-tract also includes the installation of a packaged booster pump station off-site.

Power in Numbers

2020

Project Completed

2,500,000

Project Cost